Recent Contracts
1 Project Rhyl flats offshore wind farm
Client : MT Hojgaard
Contract Value : £250K
Contract Description
Installation of internal lighting, emergency lighting, cable tray, ladder racking and installation of navigation lighting and fog detection and warning equipment. Completed Aug 2010

2 Project Walney 1 offshore wind farm
Client : Siemens PLC
Contract Value : £140K
Contract Description
Construction of new 11 kv substation to supply existing mobile offices together with new welfare units and portable offices and supply 3 no 3 phase 125 amp weatherproof distribution points located at specified points around the quay. Completed June 2010

3. Project Rhyl Flats Mobilization Works
Client : N Power
Contract Value : £110 K
Contract Description
Connection of new portacabins to generator supply together with installation of street lighting and sewage pumping facilities connected to existing supplies completed Jan 2009.